COFFS BYPASS UPDATE

Construction is progressing well on the Coffs Harbour Bypass. Blasting for the Gately’s Road tunnel has begun, and some minor traffic switches have occurred at the Korora end.
Earthworks are continuing with over 1.3 million cubic meters of dirt moved so far.
Over the next few months we will see:
– Shephards Lane and Bennetts Road realignments
– Preparing tunnel portals for Roberts Hill and Shephards Lane
– Start the bridge over the Railway Line
Some of the work completed so far:
– 21 out of 34 culverts in place
– 108 out of 272 bridge piles in place
– 8 of 17 bridges under construction
Images courtesy of Transport for NSW.